2011-2013 - Tuffnells Way, Harpenden
Demolished to make way for a large 4 bedroom with massive basement.
A total of 64 contiguous piles were drilled into the ground to support the neighbouring properties before excavation began.
Support to between the 2 neighbouring properties was crucial while the basement was constructed.
The wall shuttering is in place ready to pour the waterproof Pudlow concrete walls.
Each level had quite a number of steel beams installed as well as the solid blockwork walls.
The steel frame being installed prior to the cut roof going over.
The completed roof finish.
Curved doors were installed below the cantilevered steel beam.
Project Details
Project Type: New Build
Contract Value: £610,000
Warranty Provider: NHBC
​
Programme: Incomplete
Following the demolition of the existing house, the land was clear to build a new family home. A new 5 bedroom house with 4 bedrooms and a garage was constructed
​
The house has a "Pudlow" waterproof concrete basement slab and retaining walls. Added to this was the limited working space we had to construct the basement between the 2 neighbouring houses. So,, part of the temporary works design to install 64 contiguous piles in order to ensure that there can be no risk of settlement to these properties.
​